New Construction

Lock Up vs Fixing Stage: Key Differences in Building

Published: 3 January 2024
8 min read
7,920 views
House interior during construction showing lock up and fixing stages

Last updated: 15 May 2026

When does a new home reach lock up stage, and what still needs to happen before the fixing stage begins?

Many homeowners hear these terms from their builder, lender or site supervisor, but the difference is not always clear. Understanding lock up vs fixing stage helps you check whether the work is complete before you approve a progress payment, book a construction stage inspection, or allow the next trade to continue.

In Victoria, lock-up stage is reached when the external wall cladding and roof covering are fixed, the flooring is laid, and external doors and windows are installed.

The fixing stage includes internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards being fitted and fixed in position.

For owners, the main risk is timing. If a lock up stage inspection, pre plaster inspection, or fixing stage inspection is missed, some defects may be covered by plasterboard, tiles, cabinetry or flooring. Understanding lock up vs fixing stage helps you check whether the work is complete before you approve a progress payment, book construction stage inspections, or allow the next trade to continue.

Understanding the distinction between lock-up and fixing stages is not just about construction terminology. It directly impacts your ability to identify defects at the right time and ensure your builder delivers quality workmanship throughout the project.

Need Clear Evidence for a Building Defect?

Get an independent defect investigation report that documents the issue, likely cause, photos, and repair guidance before the dispute grows.

Book a Defect
Investigation Report

Lock Up vs Fixing Stage: Quick Comparison

Comparison pointLock Up StageFixing Stage
Main purposeMakes the home weather-protected and secureCompletes major internal fit-out items
What the stage meansExternal wall cladding and roof covering are fixed, flooring is laid, and external doors and windows are installed.Internal cladding, architraves, skirting, internal doors, built-in shelves, baths, basins, sinks, cabinets and cupboards are fitted and fixed.
NSW wordingAll doors, windows and roofing are installed so the home can be locked and kept secure.NSW commonly refers to the next internal works as fit-out, including lights, power points, tapware, cabinets, benchtops, baths, basins and shower screens.
Queensland wordingSimilar to enclosed stage, where external cladding, roof, flooring, external doors and external windows are fixed.Fixing stage, where internal linings, trims, room doors, wet area items, shelves, cabinets and cupboards are fitted.
What owners should checkRoof covering, gutters, flashings, cladding, windows, external doors, flooring, water entry risks and visible frame areas.Internal doors, skirting, architraves, cabinets, wet areas, fixtures, tiling, flooring, paint and visible finishes.
Inspection to bookLock up stage inspection and, where needed, pre plaster inspection before wall linings hide defects.Fixing stage inspection before the build moves closer to practical completion or handover.
Payment linkOften linked to the lock-up progress payment. In Victoria, a full-build contract commonly allocates 35% at lock-up.Often linked to the fixing progress payment. In Victoria, a full-build contract commonly allocates 25% at fixing.
Key risk if skippedDefects in the shell, roof, windows, cladding or water protection may be covered or harder to access later.Poor fit-off, damaged finishes, incomplete items or non-compliant fixtures may carry through to handover.

What Is Lock Up Stage in Construction?

The lock-up stage is the point where the home can be secured and protected from weather. It usually means the roof, external wall cladding, flooring, external doors and external windows are installed. A lock-up pre-plaster inspection can help identify issues before internal linings hide frame, roofing, window, door, cladding, plumbing and electrical concerns.

In NSW, lock-up is described as the stage where all doors, windows and roofing are installed, allowing the home to be locked and kept secure.

This stage is not the same as completion. Once the home is secure, weatherproofers, plumbers, electricians, plasterers, tilers and carpenters may still need to complete their work.

AreaWhat to check during a lock up stage inspection
RoofRoofing, gutters, downpipes, flashing and visible water entry risks
External claddingBrickwork, render, weatherboards, flashings and weep holes
Windows and external doorsInstallation, seals, locks, alignment and gaps
FlooringStructural flooring laid where required
Frame visibilityVisible frame areas checked before wall linings cover them
Services rough-inElectrical, plumbing, HVAC and data locations before plasterboard
WeatherproofingGaps, leaks, poor sealing and drainage concerns

Key Activities Completed at Lock-Up

Several major construction elements must be completed before a building reaches lock-up stage. These include the following essential components.

ComponentDescriptionQuality Indicators
Structural FrameComplete wall framing, roof trusses, and load-bearing elementsStraight walls, level floors, plumb door frames
RoofingRoof covering, sarking, gutters, and downpipes installedWatertight, properly fixed tiles or sheeting, adequate falls
External CladdingBrick veneer, rendered walls, weatherboards, or other claddingConsistent finish, proper flashings, weep holes functional
Windows and DoorsExternal windows and doors installed with weather sealsProperly sealed, operable locks, weatherstripping intact
Fascias and EavesFascia boards, eave linings, and external trims completedStraight lines, proper paint finish, adequate ventilation

Structural Significance of Lock-Up

The lock-up stage is significant because it marks the completion of the building's structural shell. At this point, the major load-bearing elements, including the foundation, frame, and roof structure, are in place and can be assessed for quality and compliance with engineering specifications.

  • Weather protection: The building is now protected from rain, wind, and temperature extremes, allowing interior work to proceed regardless of weather conditions
  • Secure environment: With lockable doors and windows, the site becomes more secure, reducing risk of theft or vandalism of materials and fixtures
  • Progress payment milestone: Lock-up typically triggers a significant progress payment under most building contracts, making inspection particularly important
  • Inspection opportunity: This is the last opportunity to inspect structural elements before they are covered by internal linings

Common Activities During Lock-Up Stage

While the building becomes weatherproof at lock-up, several important activities occur during and immediately following this stage to prepare for interior finishing work.

Insulation Installation

With the building envelope complete, insulation can be installed in walls and ceilings. This includes bulk insulation batts, reflective foil sarking, and acoustic insulation where required. Proper installation is critical for thermal performance and compliance with energy efficiency requirements under the National Construction Code.

Rough-In Services

Plumbing and electrical rough-in work typically occurs around lock-up stage. This involves running pipes, cables, and conduits through the frame before wall linings are installed. The rough-in stage is critical for detecting defects in services that will become hidden once plasterboard is fixed.

  • Water supply pipes and drainage installed to correct positions
  • Electrical cables run through frame with switch and power point boxes positioned
  • HVAC ductwork installed where applicable
  • Communication and data cabling roughed in

Drywall and Flooring Preparation

Preparation for internal linings begins at lock-up stage. This includes installing flooring underlayment, preparing surfaces for plasterboard, and ensuring all structural elements are ready for finishing work. Any frame adjustments needed for straight walls and level ceilings should be addressed before plasterboard installation.

Initial Paint and Protective Coatings

External elements that require paint protection, such as fascias, bargeboards, and timber trim, receive their initial coats during the lock-up stage. This protects these elements from weather damage while internal work proceeds.

Common Defects Found During a Lock Up Stage Inspection

Common defects found during a lock up stage inspection include:

  • Poor window or door sealing
  • Incomplete roof flashings
  • Cladding gaps
  • Blocked or missing weep holes
  • Damaged sarking
  • Frame movement or misalignment
  • Poor cavity clearance
  • Early water entry signs
  • Rough-in plumbing or electrical placement issues

What Is Fixing Stage in Construction?

The fixing stage represents the transition from structural construction to finishing work. This stage focuses on installing fixtures, addressing defects, and completing the interior to a standard ready for occupation. The name derives from the process of attaching or fixing interior elements to the structure.

Key Activities During Fixing Stage

The fixing stage is the internal fit-out stage. This is when many of the home’s visible interior items are fitted, fixed and checked against the contract.

In Queensland, the QBCC New Home Construction Contract defines fixing stage as the stage when internal linings, architraves, cornices, skirting, room doors, baths, shower trays, wet area tiling, built-in shelves, built-in cabinets and built-in cupboards are fitted and fixed in position.

NSW’s MyHome Planner uses the term fit-out for the stage where internal fittings and fixtures are ready to be installed, including lights, power points, tapware, cabinets, benchtops, baths, basins and shower screens.

AreaWhat to check during a fixing stage inspection
Internal doorsSwing, latches, handles, alignment and clearance
Skirting and architravesGaps, poor joins, loose sections and uneven lines
Cabinets and cupboardsLayout, damage, level installation and door alignment
Wet areasBaths, basins, shower trays, tiling, tapware and sealing
FlooringChips, hollow tiles, scratches, gaps and level changes
Electrical fit-offPower points, switches, lights and visible finish quality
Paint and finishesRuns, missed areas, rough patches and trade damage
ActivityDescriptionQuality Considerations
Defect RectificationAddressing issues identified in previous stage inspectionsVerify all noted defects have been properly corrected
Trim and Architrave InstallationDoor architraves, skirting boards, window sills, and decorative trimTight joints, consistent reveal, proper mitres, no gaps
Fixture HookupsConnecting plumbing fixtures, power points, and appliancesWatertight connections, correct wiring, functional operation
Flooring InstallationTimber, tiles, carpet, vinyl, or other floor coveringsLevel surface, proper adhesion, consistent patterns, clean cuts
Paint Touch-UpsFinal paint coats and touch-ups after fixture installationConsistent colour, no runs or drips, clean edges around fixtures
Final CleaningBuilder's clean to remove construction debris and prepare for handoverClean windows, clear debris, remove labels and protective films

Detailed Breakdown of Fixing Stage Activities

Addressing Defects from Previous Stages

A critical component of the fixing stage is rectifying defects identified during earlier inspections. This includes addressing frame alignment issues visible in plasterboard, fixing waterproofing concerns in wet areas, and correcting any structural deficiencies noted at lock-up.

Defect rectification during fixing stage should be thorough because this is often the last opportunity before practical completion. Issues that remain unaddressed may become subject to warranty claims or disputes during the defects liability period.

Completing Interior Trim Work

The fixing stage sees the installation of all decorative and functional trim elements that give the home its finished appearance.

  • Door architraves: Timber or MDF trim surrounding door frames, requiring precise mitred corners and consistent reveals
  • Skirting boards: Base trim connecting walls to floors, hiding expansion gaps and providing a finished transition
  • Window sills and reveals: Interior trim completing window installations with proper falls for condensation drainage
  • Cornices: While often installed earlier, cornice joints and corners are finished during fixing stage

Final Fixture Hookups

The rough-in work completed at lock-up stage now receives its final fixtures and connections.

  • Plumbing fixtures: Basins, toilets, showers, baths, and tapware installed and connected to water supply and drainage
  • Electrical fixtures: Switches, power points, light fittings, and exhaust fans connected and tested
  • Kitchen appliances: Cooktop, oven, rangehood, and dishwasher installed and connected
  • Laundry equipment: Washing machine taps, dryer vents, and trough connections completed

Flooring Installation

Floor coverings are typically one of the last elements installed to prevent damage from ongoing construction activities. The fixing stage sees the completion of all flooring types specified in the building contract.

  • Timber and laminate floating floors with appropriate expansion gaps
  • Ceramic and porcelain tiles with consistent grout lines and proper adhesion
  • Carpet installation with correct underlay and professionally stretched fitting
  • Vinyl and resilient flooring with seamless joints and proper edge treatment

Final Painting and Touch-Ups

While initial painting occurs before fixing stage, the installation of fixtures and trim inevitably causes minor damage that requires attention.

  • Touch-up painting around door frames and hardware
  • Final coat on skirting boards and architraves
  • Repair of scuffs and marks from fixture installation
  • External paint completion and touch-ups as needed

Final Cleaning and Preparation

The fixing stage concludes with a comprehensive builder's clean that prepares the dwelling for handover.

  • Removal of all construction debris, packaging, and materials
  • Cleaning of all windows, mirrors, and glass surfaces
  • Removal of protective films from appliances and fixtures
  • Vacuuming of all floor surfaces and wiping of benchtops
  • External site clean-up and removal of temporary structures

Common Defects Found During a Fixing Stage Inspection

Common defects found during a fixing stage inspection include:

  • Uneven skirting
  • Poor architrave joins
  • Cabinet misalignment
  • Damaged benchtops
  • Chipped tiles
  • Poor silicone work
  • Paint defects
  • Door clearance issues
  • Leaking tapware
  • Missing or incomplete fixtures

Preparing for NCAT, VCAT or QCAT?

If your matter may move toward a tribunal or court, an expert witness report can help present defects, workmanship issues, incomplete works, and repair opinions in a clearer format.

View Expert Witness
Report Services

Lock Up Stage Inspection vs Fixing Stage Inspection

Inspection typeBest timingWhat it checks
Lock up stage inspectionBefore internal linings cover key areasRoof, cladding, windows, external doors, frame visibility and water entry risks
Pre plaster inspectionBefore plasterboard or wall linings are installedRough-in plumbing, electrical wiring, insulation, framing and hidden areas
Fixing stage inspectionOnce internal fit-out items are installedDoors, skirting, architraves, cabinets, fixtures, tiling, flooring and finishes
Pre handover inspectionBefore practical completionFinal defects, incomplete items, damage and readiness for handover

NSW Government says homeowners may want to have an architect or building consultant inspect the work at each stage to confirm it is being done properly and to contract specifications and drawings.


What Happens Between Lock Up and Fixing Stage?

This section should be added to the live article because it directly targets the missing keywords what happens after lock up stage, pre plaster inspection, pre lining inspection, rough-in plumbing and electrical, and construction stage inspections.

Between the lock-up stage and fixing stage, a lot of hidden work is completed. This can include rough-in plumbing, electrical wiring, insulation, waterproofing, plasterboard and internal lining preparation.

NSW’s MyHome Planner says wiring and pipes for power, water and gas are installed by licensed electricians and plumbers during the frame and external wall phase.

A pre-plaster inspection, also called a pre-lining inspection, is useful before plasterboard is installed because many frame, service and insulation issues become harder to see once walls and ceilings are closed.

Build pointKeyword to targetInspection to book
Frame completeframe stage inspectionFrame inspection
External shell completelock up stage inspectionLock-up inspection
Before plasterboardpre plaster inspection, pre lining inspectionPre-plaster inspection
Internal fit-out installedfixing stage inspectionFixing inspection
Before handoverpre handover inspection, practical completion inspectionHandover inspection

Key Differences Between Lock-Up and Fixing Stages

Understanding the fundamental differences between these two construction stages is essential for effective project management and quality control. While both represent important milestones, their focus, activities, and implications for defect detection differ significantly.

Structural Focus vs. Detail Focus

The most fundamental difference between lock-up and fixing stages lies in their respective focus areas.

AspectLock-Up StageFixing Stage
Primary FocusStructural integrity and weather protectionInterior finishing and aesthetic completion
Work TypeMajor construction and building envelopeFine details and finishing touches
Defect ImpactStructural defects, long-term building performanceAesthetic defects, functionality of fixtures
Rectification CostHigh cost if defects found laterGenerally lower cost to rectify
Inspection PriorityFrame alignment, roof integrity, waterproofingFinish quality, fixture operation, completeness
Timeline PositionMid-construction, approximately 60% completeNear completion, approximately 90% complete
Progress PaymentTypically 35% to 40% of contract valueTypically 15% to 20% of contract value

Significant Construction vs. Finishing Tasks

The nature of work at each stage differs dramatically in scale, complexity, and the tradespeople involved.

Lock-Up Stage Characteristics

  • Heavy construction: Work involves structural elements like framing, roofing, and external cladding that form the building's skeleton
  • Multiple trades simultaneously: Framers, roofers, bricklayers, and window installers often work concurrently
  • Weather dependent: External work can be affected by rain, wind, and temperature extremes
  • Major equipment required: Cranes, scaffolding, and heavy machinery are commonly used
  • Significant material deliveries: Large quantities of timber, steel, bricks, and roofing materials arrive on site

Fixing Stage Characteristics

  • Interior focus: Work occurs primarily inside the weatherproof building envelope
  • Sequential trades: Work tends to follow a sequence, with plasterers preceding painters, who precede floor layers
  • Weather independent: Most work can proceed regardless of external conditions
  • Hand tools predominant: Work involves hand tools and smaller power tools rather than heavy equipment
  • Fixture deliveries: Smaller, more frequent deliveries of fixtures, appliances, and finishing materials

Inspection Priorities at Each Stage

The inspection focus differs significantly between lock-up and fixing stages, reflecting the different risks and opportunities at each point.

Lock-Up Inspection Priorities

  • Frame alignment using laser levels and plumb bobs
  • Roof installation quality, including tile bedding and flashing
  • Window and door installation, including weatherseals and hardware
  • External cladding, including weep holes and cavity clearance
  • Sarking and insulation installation compliance
  • Rough-in plumbing and electrical before wall closure

Fixing Stage Inspection Priorities

  • Plasterboard quality, including joints, corners, and finish
  • Paint finish consistency and coverage
  • Trim installation, including mitres, reveals, and gaps
  • Fixture operation and connection quality
  • Flooring installation and transitions
  • Overall completion and readiness for handover

Consequences of Missing Defects

The implications of failing to identify defects differ substantially between the two stages.

Lock-Up Stage Defect Consequences

Defects missed at lock-up stage often become hidden behind wall linings and can have severe long-term consequences.

  • Frame misalignment: Results in doors that do not close properly, cracked plasterboard, and uneven floors throughout the building's life
  • Roofing defects: Lead to water ingress, ceiling damage, mould growth, and timber rot that may not become apparent for years
  • Waterproofing failures: Cause structural damage, mould issues, and potential health hazards that are extremely expensive to rectify
  • Plumbing rough-in issues: Can result in concealed leaks causing timber rot, mould, and eventual failure

Fixing Stage Defect Consequences

While still important, defects at fixing stage are generally more visible and easier to rectify.

  • Paint defects: Can be touched up or repainted relatively easily
  • Trim issues: Gaps and poor mitres can be corrected without major disruption
  • Fixture problems: Can usually be adjusted or replaced with minimal impact on other work
  • Flooring defects: May require section replacement but are generally accessible for repair

Recommendations for Managing Lock-Up and Fixing Stages

Effective management of both stages requires proactive communication, careful scheduling, and engagement of professional inspectors. The following recommendations will help ensure quality outcomes at each stage.

Communication with Your Builder

Clear, consistent communication with your builder is essential throughout the construction process, but particularly at these key stages.

  • Request advance notice: Ask your builder to provide at least one week's notice before reaching lock-up and fixing stages to allow time to arrange inspections
  • Document discussions: Follow up verbal conversations with written confirmation via email to create a clear record of agreements
  • Clarify inclusions: Ensure you understand exactly what is included at each stage under your building contract to avoid disputes about completeness
  • Request progress photos: Regular photographic updates help you monitor progress and identify potential issues before stage inspections
  • Attend site meetings: Where possible, attend regular site meetings to discuss progress, address concerns, and maintain a positive working relationship

Scheduling and Timeline Management

Proper scheduling ensures inspections occur at the optimal time and that any defects can be addressed before work proceeds.

  • Book inspectors early: Engage your independent inspector before construction begins so they can schedule inspections at critical points
  • Allow rectification time: Build buffer time into your schedule for defect rectification between stages
  • Coordinate with progress payments: Time inspections to occur before progress payments are due, giving you leverage for defect rectification
  • Plan for weather delays: Recognise that lock-up stage in particular may be affected by weather, so maintain flexibility in scheduling
  • Track milestone dates: Maintain a record of when each stage is reached for warranty and contract purposes

Inspection Protocols

Establishing clear inspection protocols maximises the value of professional inspections at each stage.

  • Use qualified inspectors: Engage inspectors with appropriate qualifications, licensing, and professional indemnity insurance
  • Attend inspections when possible: Being present allows you to see defects firsthand and ask questions about their significance
  • Request detailed reports: Ensure reports include photographs, specific locations, and severity assessments for all identified defects
  • Compare reports to contract: Review inspection findings against your building contract specifications to identify non-compliance
  • Follow up systematically: Create a defect register and track rectification progress until all items are satisfactorily addressed

Engaging Professional Inspectors

Professional independent inspectors provide expertise and objectivity that protects your investment throughout construction.

Why Professional Inspections Matter

  • Technical expertise: Licensed inspectors understand Australian Standards, the National Construction Code, and industry best practices
  • Specialised equipment: Professionals use laser levels, moisture meters, thermal imaging, and other tools to detect defects not visible to the untrained eye
  • Independence: Unlike council or certifier inspections, independent inspectors work solely in your interests without conflicts
  • Documentation: Professional reports provide evidence for defect claims and protect your position in any disputes
  • Experience: Experienced inspectors have seen countless builds and can quickly identify common defects and areas of concern

What to Look for in an Inspector

  • Relevant building or engineering qualifications
  • Current professional indemnity insurance
  • Membership in professional associations
  • Positive reviews and references from previous clients
  • Clear fee structure and scope of service
  • Availability to conduct inspections at short notice when needed

Inspection Package Considerations

Many inspection companies offer packages covering multiple construction stages at a reduced overall cost compared to booking individually. A typical comprehensive inspection package might include the following stages.

  • Slab inspection before concrete pour
  • Frame stage inspection
  • Lock-up stage inspection
  • Waterproofing inspection in wet areas
  • Fixing stage inspection
  • Practical completion inspection

Progress Payment Considerations

Both lock-up and fixing stages typically trigger progress payments under standard building contracts. Managing these payments strategically helps ensure defects are addressed.

  • Review contract terms: Understand exactly what must be completed before each progress payment becomes due
  • Inspect before paying: Always complete your inspection before making progress payments to maintain leverage for rectification
  • Document incompleteness: If work is not fully complete at the claimed stage, document this in writing before making any payment
  • Withhold proportionally: Your contract may allow you to withhold an amount proportional to identified defects until rectification
  • Seek advice if uncertain: If disputes arise over stage completion or defects, seek advice from a building dispute resolution service or construction lawyer

Lock Up Stage vs Fixing Stage Progress Payments

This section should replace the current progress payment section because the live blog gives risky advice about withholding payment. The current blog says owners may withhold payment proportional to defects, but NSW guidance says progress payments should be made as agreed in the contract only after the work has been completed, and non-payment can lead to legal recovery action.

The progress payment lock up stage is important because lock-up often triggers a large payment. In Victoria, the standard payment schedule for a full build includes 10% at base, 15% at frame, 35% at lock-up and 25% at fixing.

NSW Government says contracts over $20,000 must include a progress payment schedule, and progress payments must match the work carried out.

Payment stageKeyword insertedOwner action
Lock-up paymentprogress payment lock up stageConfirm lock-up is complete before paying
Fixing paymentfixing stage progress paymentConfirm internal fit-out work is complete before paying
Final paymentpractical completion inspectionBook a pre handover inspection before final payment

Is Enclosed Stage the Same as Lock Up Stage?

In Queensland, enclosed stage is often used instead of lock up stage.

The QBCC New Home Construction Contract General Conditions define enclosed stage as the stage when external wall cladding is fixed, the roof is fixed, structural flooring is laid, external doors are fixed and external windows are fixed, even if some items are temporary.


When Should You Book Construction Stage Inspections?

Book construction stage inspections before the builder moves to the next stage. This gives you time to identify issues while the work is still visible.

StageInspection keywordWhy it matters
Lock-uplock up stage inspectionChecks the building shell before internal linings hide defects
Between lock-up and fixingpre plaster inspection or pre lining inspectionChecks rough-in services and hidden work before plasterboard
Fixingfixing stage inspectionChecks internal fit-out quality and incomplete items
Practical completionpre handover inspectionChecks final defects before handover

Need Help Documenting Building Defects?

Speak with Owner Inspections about your defect concerns, photos, builder correspondence, inspection needs, or next steps before making a claim.

Contact Owner
Inspections

Frequently Asked Questions

What is the difference between lock up and fixing stage?

The difference between lock up vs fixing stage is that lock-up focuses on the external building shell, while fixing focuses on the internal fit-out. Lock-up includes external cladding, roof covering, flooring, external doors and windows, while fixing includes internal cladding, architraves, skirting, doors, cabinets, cupboards, baths, basins and sinks.

What is included in lock up stage?

The lock up stage includes external wall cladding, roof covering, flooring, external doors and external windows.

What is included in fixing stage?

The fixing stage includes internal cladding, architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards fitted and fixed in position.

What happens after lock up stage?

After lock up stage, internal trades may complete plumbing, electrical, plastering, tiling, carpentry and fit-out preparation. NSW’s MyHome Planner says plumbers, electricians, plasterers, tilers and carpenters can complete their work once the home is secure.

Is fixing stage the same as fit out stage?

The fixing stage and fit out stage are closely related terms. NSW’s MyHome Planner uses fit-out for internal fittings and fixtures such as lights, power points, tapware, cabinets, benchtops, baths, basins and shower screens.

Is enclosed stage the same as lock up stage?

In Queensland, enclosed stage is a contract term that is similar to lock up stage. QBCC defines enclosed stage as including external wall cladding, roof, structural flooring, external doors and external windows being fixed.

Should I get a lock up stage inspection?

Yes. A lock up stage inspection helps check the roof, cladding, external doors, windows, visible frame areas and weatherproofing risks before internal linings cover parts of the build.

Should I get a fixing stage inspection?

Yes. A fixing stage inspection helps check internal doors, skirting, architraves, cabinets, cupboards, wet area fittings, flooring, paint and visible finishes before the project moves closer to handover.

Can I pay the lock up progress payment before inspection?

Avoid paying before the work is complete. NSW Government says progress payments must match the work carried out.

How long between lock up and fixing stage?

The time between lock up stage and fixing stage depends on the builder, contract, trade availability, weather, internal lining work and fit-out schedule. The live article currently says fixing usually begins 4 to 8 weeks after lock-up, but this should be framed as a guide only because timing varies by project.

Key Takeaways

  • The lock-up stage marks completion of the building envelope, creating a secure, weatherproof structure with frame, roofing, cladding, and external windows and doors in place.
  • The fixing stage focuses on interior finishing including trim work, fixture hookups, flooring, final painting, defect rectification, and preparation for handover.
  • Lock-up inspection is critical because structural and services defects become hidden once wall linings are installed, making later rectification extremely expensive.
  • Fixing stage defects are generally more visible and accessible for repair compared to concealed lock-up stage defects.
  • Professional independent inspections at both stages protect your investment and provide leverage for defect rectification before progress payments.
  • Clear communication with your builder, proper scheduling, and systematic defect tracking are essential for quality outcomes.
  • Lock-up typically triggers a progress payment of 35% to 40% of contract value, while fixing stage triggers approximately 15% to 20%.
  • Engaging qualified inspectors with appropriate licensing, insurance, and experience provides technical expertise and objective assessment throughout construction.

Need Construction Stage Inspections?

Our licensed inspectors cover Sydney, Melbourne, and all major Australian cities.

Book Stage Inspections

Related Topics:

lock up stagefixing stageconstruction phasesnew home constructionAustralia